Do You Need Building Regulations for a Boiler, Windows or Rewiring?
Published 26 November 2026 · Propvio Guides
General information, not legal advice
Many people assume a straight replacement needs no paperwork. Some common jobs do need building regulations approval, even when the new item replaces an old one. This guide covers England; Wales, Scotland and Northern Ireland have their own rules.
Common Jobs That Need Approval
GOV.UK says most repairs and replacements do not need approval, except heating systems, oil tanks, fuse boxes and glazing units. Common jobs that can need it include:
- Installing or replacing a heating system, including a boiler, or adding extra radiators.
- Replacing a fuse box (consumer unit) and the electrics connected to it.
- Adding new electrical circuits, such as during a rewire.
- Changing electrics near a bath or shower.
- Replacing windows, and external doors that are more than half glazed.
- Replacing the roof covering on a pitched or flat roof.
Some jobs are exempt, such as new sockets and lights or changes to existing circuits away from baths and showers. Emergency boiler repairs do not need approval in advance. Exempt work must still meet safety standards.
The Easy Route: a Registered Installer
Installers registered with a competent person scheme can certify their own work, for the type of work they are registered for. You do not need to apply for approval yourself.
The installer tells the council about the work for you. GOV.UK says you should get a certificate within 8 weeks of completion, and it shows up in a buyer's searches when you sell. If it does not arrive, ask the installer.
GOV.UK also notes that competent person schemes have complaints procedures if there is a problem with the work.
Gas work, including fitting a gas boiler, must by law be done by an engineer on the Gas Safe Register.
If the Installer Is Not Registered
The work then needs building control approval before it starts, and there is a fee. You can apply to the council or to a registered building control approver. They inspect the work and issue a completion certificate.
Agree in writing who will apply and who pays the fee. Do not let work start until this is sorted.
How to Check an Installer Is Registered
Ask which scheme the installer belongs to, then check their name on that scheme's register. GOV.UK links to the registers for checking an installer.
Propvio's registration checker links to the main registers by trade.
Planning Permission Is Separate
Building regulations cover how work is done. Planning permission covers whether it is allowed at all.
Replacing a house's windows with similar ones does not usually need planning permission. Flats, homes in some conservation areas and listed buildings can be different. A listed building usually needs listed building consent.
Why It Matters When You Sell
A buyer's conveyancer will usually ask for certificates for boilers, windows and electrical work. A missing certificate can delay a sale.
If one is missing, see Lost FENSA Certificate, Lost Boiler Installation Certificate or Missing Electrical Certificate.
Attach each certificate to the job on Propvio when it arrives, so it is ready when you sell.
Check the Current Rules
This guide is a summary. The full rules are on GOV.UK, and your council's building control team can answer questions about a specific job.
Sources
This guide is general information, not legal, financial or professional advice. Rules change, and can differ between England, Wales, Scotland and Northern Ireland. Check the official source, or ask a qualified professional about your own situation.